# Baufritz Builder Coordination Specification ## 1. Overview This document specifies requirements that must be communicated to and coordinated with Baufritz during the design and construction phases. Baufritz builds with excellent low-emission materials (no formaldehyde, no synthetic glues, tested for 300+ pollutants) and designs for airtight envelopes — this is the ideal foundation for our clean air system. **The air system is not a retrofit. It must be designed into the structure from the beginning.** --- ## 2. Technical Room Requirements A dedicated technical room is required for the air handling equipment. This is not a utility cupboard — it needs standing access for filter changes and equipment maintenance. ### 2.1 Minimum Specifications | Parameter | Requirement | |-----------|-------------| | Floor area | 4–6 m² minimum (ideally 6–8 m²) | | Ceiling height | ≥ 2.4 m | | Access | Full-width door (≥ 900 mm), no obstructions | | Floor | Waterproof, drainable (steam humidifier condensate) | | Electrical | 3× dedicated 230V/16A circuits (MVHR, humidifier, controls) | | Lighting | Bright, shadow-free (filter inspection) | | Location | Central in building footprint (minimizes duct runs) | | Noise isolation | Sound-insulated walls/door (MVHR generates 35–45 dB) | ### 2.2 Equipment Layout ```mermaid block-beta columns 3 block:row1:3 A["G4/M5\nPre-filter\nHousing"] B["F7\nIntermediate\nHousing"] C["Activated\nCarbon\nHousing"] end block:row2:3 D["H13 HEPA\nCassette Bank\n(600×600mm panels)"] space:1 E["MVHR Unit\n(Drexel & Weiss\nor Swegon)"] end block:row3:3 F["Steam\nHumidifier\n(Condair/Hygromatik)"] G["Control\nPanel\n(KNX Gateway)"] H["Supply\nDuct\nManifold"] end style D fill:#1a5e1a,color:#fff style E fill:#1a3d5e,color:#fff style F fill:#1a5e5e,color:#fff ``` **All filter housings must be accessible from the front** with tool-free opening for filter changes. Minimum 800 mm clearance in front of each housing. --- ## 3. Duct Routing Requirements ### 3.1 Design Principles | Requirement | Detail | |------------|--------| | Duct material | Rigid galvanized steel or aluminum — **no semi-rigid flex** | | Exception | Final 0.5 m to each diffuser: flex for vibration isolation | | Sealing | All joints mastic-sealed (not tape only) | | Testing | Pressure-tested to Passivhaus duct leakage class after installation | | Velocity: main trunk | ≤ 2.0 m/s | | Velocity: branches | ≤ 1.5 m/s | | Velocity: diffuser connection | ≤ 1.0 m/s | | Main trunk diameter | 200–250 mm round (or equivalent rectangular) | | Branch diameter | 125–160 mm round | ### 3.2 Routing Constraints - **No ducts in exterior walls** — condensation risk and thermal bridging - **Dedicated vertical risers** for multi-story distribution — coordinate with structural plan - **Acoustic silencers** at MVHR outlets and before each room diffuser - **Inspection/cleaning access points** at all bends > 45° and every 6 m of straight run - **Fire dampers** at all floor/wall penetrations per DIN 4102 ### 3.3 Duct Space Requirements ```mermaid flowchart TD subgraph Ground["Ground Floor Ceiling Void"] GT["Main Supply Trunk\n200–250mm"] GB1["Branch: Living Room\n160mm"] GB2["Branch: Kitchen\n125mm (exhaust only)"] GB3["Branch: Office\n125mm"] end subgraph Upper["Upper Floor Ceiling Void"] UT["Main Supply Trunk\n200mm"] UB1["Branch: Master Bedroom\n160mm"] UB2["Branch: Leo's Room\n125mm"] UB3["Branch: Bathroom(s)\n100mm"] end TR["Technical Room"] --> GT TR --> UT style TR fill:#1a3d5e,color:#fff ``` **Baufritz must allocate ceiling void depth of ≥ 300 mm** in areas where main ducts run, or provide dedicated duct boxing. This must be shown on construction drawings. **Note**: The ceiling void is shared with the Lindner Plafotherm radiant ceiling system (see 04-flooring-ceiling-spec Section 4). On the ground floor, branch supply ducts may route through the raised floor cavity instead (see 04-flooring-ceiling-spec Section 6), potentially reducing ceiling void requirements. However, the main supply trunk and Plafotherm pipes still require adequate ceiling void depth. **Floor-to-floor structural height must be ≥ 3000 mm** to accommodate both the raised floor and ceiling system while maintaining ≥ 2500 mm usable room height (see 04-flooring-ceiling-spec Section 2). --- ## 4. Building Envelope Requirements ### 4.1 Airtightness | Parameter | Requirement | |-----------|-------------| | Blower door test (n50) | ≤ 0.6 ACH (Passivhaus standard) | | Target | 0.3 ACH if achievable | | Testing | Blower door test during construction (before interior finishing) AND after completion | Baufritz typically achieves excellent airtightness. This is critical — the air system only works if 100% of air passes through the filter stack. Every uncontrolled leak bypasses the entire system. ### 4.2 Radon Protection | Item | Specification | |------|--------------| | Radon membrane | Continuous radon-proof membrane at foundation/ground slab | | Membrane type | HDPE or bituminous, radon-tested per DIN/ISO | | Sealing | All penetrations (pipes, cables) sealed with radon-rated sealant | | Sub-slab ventilation | Provision for passive sub-slab depressurization (can be activated later if needed) | | Monitoring | Radon sensor in lowest habitable room, connected to Home Assistant | **Note**: The Bremen/Grasberg area is generally low radon risk per BfS (Federal Office for Radiation Protection) maps, but radon protection is inexpensive at construction stage and expensive to retrofit. Specify it regardless. **Raised floor compatibility**: The Lindner NORTEC Doppelboden pedestal system must be anchored with adhesive bonding only — no mechanical fixings that penetrate the radon membrane. Verify adhesive compatibility with the membrane material (see 04-flooring-ceiling-spec Section 7.5). ### 4.3 Thermal Bridge Prevention Baufritz excels at thermal-bridge-free construction. Verify: - No thermal bridges at window reveals, sills, lintels - No thermal bridges at floor/wall junctions - No thermal bridges at balcony connections (if any) - Surface temperatures never below dewpoint at any point (prevents condensation → mold) --- ## 5. MVHR Specification for Baufritz ### 5.1 Unit Selection Specify to Baufritz that the MVHR unit must meet: | Parameter | Minimum | Preferred | |-----------|---------|-----------| | Available static pressure | 450 Pa | ≥ 500 Pa | | Airflow capacity | 400 m³/h | 450 m³/h | | Heat recovery | 85% | ≥ 90% | | Fan motor | EC variable speed | EC variable speed | | Bypass | Summer bypass with motorized flap | Automatic | | Controls interface | Modbus | KNX native | | External filter box | Compatible | Designed for | ### 5.2 Baufritz-Typical vs. Our Requirements Baufritz typically installs standard residential MVHR units (e.g., Zehnder ComfoAir Q350, Paul Novus 300). These are excellent units but designed for F7/F9 filtration with ~200–250 Pa system pressure. **Our H13 whole-house requirement means upgrading to a higher-pressure unit.** This must be specified early because: - The MVHR unit dimensions affect technical room layout - Higher-pressure units may have different duct connection sizes - Electrical requirements may differ (larger EC motors) - Noise characteristics change — sound insulation may need upgrading --- ## 6. Garage Separation If the house includes an attached garage: | Requirement | Detail | |------------|--------| | Pressure separation | Garage at negative pressure relative to house | | No shared air volume | No door directly from garage to conditioned space without airlock | | Separate exhaust | Garage has its own exhaust fan with timer/CO sensor | | Sealing | All wall/ceiling penetrations between garage and house fully sealed | | CO sensor | In garage, interlocked with garage exhaust fan | **Garage exhaust fumes (CO, NOx, PM, benzene) are extremely hazardous. Zero tolerance for garage air entering the conditioned space.** --- ## 7. Kitchen Exhaust Specification | Requirement | Detail | |------------|--------| | Type | Ducted to outside — NOT recirculating | | Backdraft damper | Motorized, closes when hood is off | | Duct material | Stainless steel or galvanized (grease-rated) | | Interlock | Activates MVHR boost mode for make-up air | | Separation | Never connected to the MVHR system | | Fire safety | Fire damper at wall penetration | --- ## 8. Electrical & Wiring Coordination ### 8.1 Technical Room Electrical | Circuit | Rating | Purpose | |---------|--------|---------| | MVHR dedicated | 230V / 16A | MVHR unit power | | Humidifier dedicated | 230V / 16A (or 400V / 3-phase) | Steam humidifier (high wattage) | | Controls | 230V / 10A | KNX power supply, gateway, sensors | | Backup/spare | 230V / 16A | Future expansion | ### 8.2 Building-Wide Wiring | Item | Specification | |------|--------------| | KNX bus cable | To every zone (MVHR dampers, sensors) | | Cat6a shielded | To every room (sensor data, future-proofing) | | 230V at sensor points | USB power for sensor units | | Outdoor sensor cable | Weatherproof, north wall | | ΔP sensor cabling | 5× runs from filter housing to control panel | **All wiring for the air system must be specified on Baufritz's electrical plan before wall construction begins.** Retrofit wiring in a sealed timber-frame house is extremely difficult and expensive. --- ## 9. Construction Phase Checkpoints ### 9.1 During Construction | Phase | Checkpoint | |-------|-----------| | Foundation | Radon membrane installed and sealed at all penetrations | | Framing | Duct routing voids verified, vertical risers in place | | Framing | Ceiling void dimensions verified for Plafotherm + MVHR trunk | | Pre-close | First blower door test (target ≤ 0.6 n50) | | Pre-close | All duct runs installed, mastic-sealed, pressure-tested | | Pre-close | All KNX/Cat6 wiring installed and tested | | Interior finishing | Plafotherm ceiling suspension and panels installed | | Interior finishing | Ceiling heating circuit pressure-tested | | Interior finishing | Raised floor pedestals installed, subfloor leveling verified | | Interior finishing | Under-floor services (ducts, wiring) installed and pressure-tested | | Interior finishing | Floor panels and WOODline parquet tiles installed | | Interior finishing | Verify no ducts compressed or kinked by finishing work | | Completion | Final blower door test | | Completion | Commission MVHR, set airflows, balance dampers / AirHybrid panels | | Completion | Commission ceiling heating/cooling, verify surface temperatures | | Completion | Commission sensors, verify readings, connect to Home Assistant | ### 9.2 Commissioning Verification | Test | Acceptance Criteria | |------|-------------------| | Blower door (n50) | ≤ 0.6 ACH | | Duct leakage | Passivhaus class | | Room-by-room airflow | Within ±10% of design spec | | House positive pressure | +3 to +5 Pa vs. outside | | CO₂ decay test | < 800 ppm within 30 min of occupancy end | | PM2.5 indoor vs. outdoor | Indoor < 10% of outdoor | | Noise at diffusers | < 25 dB(A) per diffuser | --- ## 10. Timeline Integration | Baufritz Phase | Air System Action | Lindner Floor/Ceiling Action | |----------------|-------------------|------------------------------| | Initial design | Specify MVHR unit, technical room size, duct routing | Confirm raised floor + Plafotherm, specify cavity heights and floor-to-floor height (≥ 3000 mm) | | Detailed planning | Approve duct routing on drawings, specify all penetrations | Lindner layout drawings for floor and ceiling, coordinate with MVHR plan | | Pre-fabrication | Confirm radon membrane spec, duct void dimensions | Verify subfloor level tolerance and ceiling anchor points in prefab panels | | Factory build | Verify duct voids in prefab wall/floor panels | No impact (Lindner systems installed on-site) | | On-site assembly | Supervise duct installation, first blower door test | Install ceiling system, then floor pedestals and cavity services | | Finishing | Sensor wiring, diffuser installation | Parquet tile installation, floor and ceiling commissioning | | Handover | Full commissioning, sensor calibration, HA setup | Heating/cooling commissioning, AirHybrid airflow verification |