Files
house-spec/specs/03-baufritz-coordination-spec.md

16 KiB
Raw Blame History

Baufritz Builder Coordination Specification

1. Overview

This document specifies requirements that must be communicated to and coordinated with Baufritz during the design and construction phases. Baufritz builds with excellent low-emission materials (no formaldehyde, no synthetic glues, tested for 300+ pollutants) and designs for airtight envelopes — this is the ideal foundation for our clean air system.

The air system is not a retrofit. It must be designed into the structure from the beginning.

The house includes a reinforced concrete cellar housing a home datacenter (4x 42U racks, 10 kW cooling) and goods elevator. The cellar is built first; the Baufritz timber-frame is erected on top. See 06-datacenter-spec for full cellar, elevator, and datacenter specifications.


2. Technical Room Requirements

A dedicated technical room is required for the air handling equipment. This is not a utility cupboard — it needs standing access for filter changes and equipment maintenance.

2.1 Minimum Specifications

Parameter Requirement
Floor area 810 m² (air system + water treatment — see 05-water-system-spec Section 11.1)
Ceiling height ≥ 2.4 m
Access Full-width door (≥ 900 mm), no obstructions
Floor Waterproof, drainable (steam humidifier condensate)
Electrical 3× dedicated 230V/16A circuits (MVHR, humidifier, controls)
Lighting Bright, shadow-free (filter inspection)
Location Central in building footprint (minimizes duct runs)
Noise isolation Sound-insulated walls/door (MVHR generates 3545 dB)

2.2 Equipment Layout

block-beta
    columns 3

    block:row1:3
        A["G4/M5\nPre-filter\nHousing"] B["F7\nIntermediate\nHousing"] C["Activated\nCarbon\nHousing"]
    end

    block:row2:3
        D["H13 HEPA\nCassette Bank\n(600×600mm panels)"] space:1 E["MVHR Unit\n(Drexel & Weiss\nor Swegon)"]
    end

    block:row3:3
        F["Steam\nHumidifier\n(Condair/Hygromatik)"] G["Control\nPanel\n(KNX Gateway)"] H["Supply\nDuct\nManifold"]
    end

    style D fill:#1a5e1a,color:#fff
    style E fill:#1a3d5e,color:#fff
    style F fill:#1a5e5e,color:#fff

All filter housings must be accessible from the front with tool-free opening for filter changes. Minimum 800 mm clearance in front of each housing.


3. Duct Routing Requirements

3.1 Design Principles

Requirement Detail
Duct material Rigid galvanized steel or aluminum — no semi-rigid flex
Exception Final 0.5 m to each diffuser: flex for vibration isolation
Sealing All joints mastic-sealed (not tape only)
Testing Pressure-tested to Passivhaus duct leakage class after installation
Velocity: main trunk ≤ 2.0 m/s
Velocity: branches ≤ 1.5 m/s
Velocity: diffuser connection ≤ 1.0 m/s
Main trunk diameter 200250 mm round (or equivalent rectangular)
Branch diameter 125160 mm round

3.2 Routing Constraints

  • No ducts in exterior walls — condensation risk and thermal bridging
  • Dedicated vertical risers for multi-story distribution — coordinate with structural plan
  • Acoustic silencers at MVHR outlets and before each room diffuser
  • Inspection/cleaning access points at all bends > 45° and every 6 m of straight run
  • Fire dampers at all floor/wall penetrations per DIN 4102

3.3 Duct Space Requirements

flowchart TD
    subgraph Ground["Ground Floor Ceiling Void"]
        GT["Main Supply Trunk\n200250mm"]
        GB1["Branch: Living Room\n160mm"]
        GB2["Branch: Kitchen\n125mm (exhaust only)"]
        GB3["Branch: Office\n125mm"]
    end

    subgraph Upper["Upper Floor Ceiling Void"]
        UT["Main Supply Trunk\n200mm"]
        UB1["Branch: Master Bedroom\n160mm"]
        UB2["Branch: Leo's Room\n125mm"]
        UB3["Branch: Bathroom(s)\n100mm"]
    end

    TR["Technical Room"] --> GT
    TR --> UT

    style TR fill:#1a3d5e,color:#fff

Baufritz must allocate ceiling void depth of ≥ 300 mm in areas where main ducts run, or provide dedicated duct boxing. This must be shown on construction drawings.

Note: The ceiling void is shared with the Lindner Plafotherm radiant ceiling system (see 04-flooring-ceiling-spec Section 4). On the ground floor, branch supply ducts may route through the raised floor cavity instead (see 04-flooring-ceiling-spec Section 6), potentially reducing ceiling void requirements. However, the main supply trunk and Plafotherm pipes still require adequate ceiling void depth. Floor-to-floor structural height must be ≥ 3000 mm to accommodate both the raised floor and ceiling system while maintaining ≥ 2500 mm usable room height (see 04-flooring-ceiling-spec Section 2).


4. Building Envelope Requirements

4.1 Airtightness

Parameter Requirement
Blower door test (n50) ≤ 0.6 ACH (Passivhaus standard)
Target 0.3 ACH if achievable
Testing Blower door test during construction (before interior finishing) AND after completion

Baufritz typically achieves excellent airtightness. This is critical — the air system only works if 100% of air passes through the filter stack. Every uncontrolled leak bypasses the entire system.

4.2 Radon Protection

Item Specification
Radon membrane Continuous radon-proof membrane at foundation/ground slab
Membrane type HDPE or bituminous, radon-tested per DIN/ISO
Sealing All penetrations (pipes, cables) sealed with radon-rated sealant
Sub-slab ventilation Provision for passive sub-slab depressurization (can be activated later if needed)
Monitoring Radon sensor in lowest habitable room, connected to Home Assistant

Note: The Bremen/Grasberg area is generally low radon risk per BfS (Federal Office for Radiation Protection) maps, but radon protection is inexpensive at construction stage and expensive to retrofit. Specify it regardless.

Raised floor compatibility: The Lindner NORTEC Doppelboden pedestal system must be anchored with adhesive bonding only — no mechanical fixings that penetrate the radon membrane. Verify adhesive compatibility with the membrane material (see 04-flooring-ceiling-spec Section 7.5).

4.3 Thermal Bridge Prevention

Baufritz excels at thermal-bridge-free construction. Verify:

  • No thermal bridges at window reveals, sills, lintels
  • No thermal bridges at floor/wall junctions
  • No thermal bridges at balcony connections (if any)
  • Surface temperatures never below dewpoint at any point (prevents condensation → mold)

5. MVHR Specification for Baufritz

5.1 Unit Selection

Specify to Baufritz that the MVHR unit must meet:

Parameter Minimum Preferred
Available static pressure 450 Pa ≥ 500 Pa
Airflow capacity 400 m³/h 450 m³/h
Heat recovery 85% ≥ 90%
Fan motor EC variable speed EC variable speed
Bypass Summer bypass with motorized flap Automatic
Controls interface Modbus KNX native
External filter box Compatible Designed for

5.2 Baufritz-Typical vs. Our Requirements

Baufritz typically installs standard residential MVHR units (e.g., Zehnder ComfoAir Q350, Paul Novus 300). These are excellent units but designed for F7/F9 filtration with ~200250 Pa system pressure.

Our H13 whole-house requirement means upgrading to a higher-pressure unit. This must be specified early because:

  • The MVHR unit dimensions affect technical room layout
  • Higher-pressure units may have different duct connection sizes
  • Electrical requirements may differ (larger EC motors)
  • Noise characteristics change — sound insulation may need upgrading

6. Garage Separation

If the house includes an attached garage:

Requirement Detail
Pressure separation Garage at negative pressure relative to house
No shared air volume No door directly from garage to conditioned space without airlock
Separate exhaust Garage has its own exhaust fan with timer/CO sensor
Sealing All wall/ceiling penetrations between garage and house fully sealed
CO sensor In garage, interlocked with garage exhaust fan

Garage exhaust fumes (CO, NOx, PM, benzene) are extremely hazardous. Zero tolerance for garage air entering the conditioned space.


7. Kitchen Exhaust Specification

Requirement Detail
Type Ducted to outside — NOT recirculating
Backdraft damper Motorized, closes when hood is off
Duct material Stainless steel or galvanized (grease-rated)
Interlock Activates MVHR boost mode for make-up air
Separation Never connected to the MVHR system
Fire safety Fire damper at wall penetration

8. Electrical & Wiring Coordination

8.1 Technical Room Electrical

Circuit Rating Purpose
MVHR dedicated 230V / 16A MVHR unit power
Humidifier dedicated 230V / 16A (or 400V / 3-phase) Steam humidifier (high wattage)
Controls 230V / 10A KNX power supply, gateway, sensors
RO booster pump 230V / 16A Reverse osmosis feed pressure (see 05-water-system-spec)
Distribution pump 230V / 10A Water distribution pressure
UV sterilizer 230V / 10A Post-storage UV-C sterilization
Recirculation pump 230V / 10A Hot water recirculation loop
Backup/spare 230V / 16A Future expansion

8.2 Main Electrical Distribution

The total house electrical demand including the cellar datacenter requires a properly sized main distribution:

Parameter Specification
Main fuse 3×80A (400V 3-phase) = ~55 kW capacity
Main distribution board Located in cellar electrical room (see 06-datacenter-spec Section 4.2)
Sub-boards Ground floor, upper floor, technical room (air/water), cellar/datacenter
Surge protection Type 1+2 SPD at main board
Metering Smart meter with Home Assistant integration

8.3 Building-Wide Wiring

Item Specification
KNX bus cable To every zone (MVHR dampers, sensors)
Cat6a shielded 2× per room (dual-purpose: data network + sensor — see 06-datacenter-spec Section 6.2)
Fiber backbone 12-core OS2 single-mode from cellar to each floor (10G+ backbone)
230V at sensor points USB power for sensor units
Outdoor sensor cable Weatherproof, north wall
ΔP sensor cabling 5× runs from filter housing to control panel

All wiring must be specified on Baufritz's electrical plan before wall construction begins. Retrofit wiring in a sealed timber-frame house is extremely difficult and expensive. The fiber and Cat6a backbone risers from the cellar must be coordinated with the elevator shaft and/or dedicated cable riser.


9. Construction Phase Checkpoints

9.1 During Construction

Phase Checkpoint
Cellar construction Reinforced concrete cellar complete, waterproofed, radon membrane sealed
Cellar construction Elevator shaft cast, anchor bolt locations verified
Cellar construction Cellar slab level tolerance verified (+/- 5 mm) for Baufritz erection
Cellar construction Electrical conduits cast into cellar slab for riser penetrations
Foundation Radon membrane continuous between cellar and ground floor
Framing Elevator shaft opening integrated into ground floor structure
Framing Duct routing voids verified, vertical risers in place
Framing Ceiling void dimensions verified for Plafotherm + MVHR trunk
Pre-close First blower door test (target ≤ 0.6 n50)
Pre-close All duct runs installed, mastic-sealed, pressure-tested
Pre-close All KNX/Cat6 wiring installed and tested
Interior finishing Plafotherm ceiling suspension and panels installed
Interior finishing Ceiling heating circuit pressure-tested
Interior finishing Raised floor pedestals installed, subfloor leveling verified
Interior finishing Under-floor services (ducts, wiring) installed and pressure-tested
Interior finishing Floor panels and WOODline parquet tiles installed
Interior finishing 316L stainless steel water supply runs installed in ceiling void
Interior finishing Water supply pressure-tested at 16 bar for 2 hours
Interior finishing All press-fit joints verified accessible via ceiling panel removal
Interior finishing Drain/waste pipes installed in floor cavity
Interior finishing Verify no ducts compressed or kinked by finishing work
Completion Final blower door test
Completion Commission MVHR, set airflows, balance dampers / AirHybrid panels
Completion Commission ceiling heating/cooling, verify surface temperatures
Completion Commission RO system, verify TDS/pH at every outlet
Completion Commission leak detection, test auto shut-off valve
Completion Elevator installed and tested
Completion Datacenter racks, cooling, UPS commissioned (see 06-datacenter-spec Section 12)
Completion Structured cabling (fiber + Cat6a) tested and certified
Completion Commission sensors, verify readings, connect to Home Assistant

9.2 Commissioning Verification

Test Acceptance Criteria
Blower door (n50) ≤ 0.6 ACH
Duct leakage Passivhaus class
Room-by-room airflow Within ±10% of design spec
House positive pressure +3 to +5 Pa vs. outside
CO₂ decay test < 800 ppm within 30 min of occupancy end
PM2.5 indoor vs. outdoor Indoor < 10% of outdoor
Noise at diffusers < 25 dB(A) per diffuser

10. Timeline Integration

Baufritz Phase Air System Action Lindner Floor/Ceiling Action Water System Action Cellar/Datacenter Action
Initial design Specify MVHR unit, technical room size (8-10 m2), duct routing Confirm raised floor + Plafotherm, specify cavity heights and floor-to-floor height (≥ 3000 mm) Confirm POE RO location, municipal water entry, reject water drain Cellar dimensions, elevator shaft location, main electrical sizing (3x80A)
Detailed planning Approve duct routing on drawings, specify all penetrations Lindner layout drawings for floor and ceiling, coordinate with MVHR plan 316L pipe routing in ceiling void, riser locations, fixture drop-down points Cellar structural drawings, elevator spec, cooling condenser location
Pre-fabrication Confirm radon membrane spec, duct void dimensions Verify subfloor level tolerance and ceiling anchor points in prefab panels Confirm ceiling void can accommodate water pipes alongside MVHR and Plafotherm Cellar construction begins (concrete, waterproofing, elevator shaft)
Factory build Verify duct voids in prefab wall/floor panels No impact (Lindner systems installed on-site) No impact (water system installed on-site) Cellar complete, slab cured, ready for Baufritz erection
On-site assembly Supervise duct installation, first blower door test Install ceiling suspension, route Plafotherm pipes Install 316L supply mains in ceiling void (same phase as Plafotherm) Elevator installed, main distribution board installed
Finishing Sensor wiring, diffuser installation Plafotherm panels, floor pedestals, parquet tiles Pressure-test pipes, install drain/waste in floor cavity, connect fixtures Datacenter fit-out: racks, cooling, cabling, UPS
Handover Full commissioning, sensor calibration, HA setup Heating/cooling commissioning, AirHybrid airflow verification RO commissioning, TDS/pH verification, leak detection test Cooling commissioning, fire detection test, HA integration