308 lines
16 KiB
Markdown
308 lines
16 KiB
Markdown
# Baufritz Builder Coordination Specification
|
||
|
||
## 1. Overview
|
||
|
||
This document specifies requirements that must be communicated to and coordinated with Baufritz during the design and construction phases. Baufritz builds with excellent low-emission materials (no formaldehyde, no synthetic glues, tested for 300+ pollutants) and designs for airtight envelopes — this is the ideal foundation for our clean air system.
|
||
|
||
**The air system is not a retrofit. It must be designed into the structure from the beginning.**
|
||
|
||
**The house includes a reinforced concrete cellar** housing a home datacenter (4x 42U racks, 10 kW cooling) and goods elevator. The cellar is built first; the Baufritz timber-frame is erected on top. See 06-datacenter-spec for full cellar, elevator, and datacenter specifications.
|
||
|
||
---
|
||
|
||
## 2. Technical Room Requirements
|
||
|
||
A dedicated technical room is required for the air handling equipment. This is not a utility cupboard — it needs standing access for filter changes and equipment maintenance.
|
||
|
||
### 2.1 Minimum Specifications
|
||
|
||
| Parameter | Requirement |
|
||
|-----------|-------------|
|
||
| Floor area | **8–10 m²** (air system + water treatment — see 05-water-system-spec Section 11.1) |
|
||
| Ceiling height | ≥ 2.4 m |
|
||
| Access | Full-width door (≥ 900 mm), no obstructions |
|
||
| Floor | Waterproof, drainable (steam humidifier condensate) |
|
||
| Electrical | 3× dedicated 230V/16A circuits (MVHR, humidifier, controls) |
|
||
| Lighting | Bright, shadow-free (filter inspection) |
|
||
| Location | Central in building footprint (minimizes duct runs) |
|
||
| Noise isolation | Sound-insulated walls/door (MVHR generates 35–45 dB) |
|
||
|
||
### 2.2 Equipment Layout
|
||
|
||
```mermaid
|
||
block-beta
|
||
columns 3
|
||
|
||
block:row1:3
|
||
A["G4/M5\nPre-filter\nHousing"] B["F7\nIntermediate\nHousing"] C["Activated\nCarbon\nHousing"]
|
||
end
|
||
|
||
block:row2:3
|
||
D["H13 HEPA\nCassette Bank\n(600×600mm panels)"] space:1 E["MVHR Unit\n(Drexel & Weiss\nor Swegon)"]
|
||
end
|
||
|
||
block:row3:3
|
||
F["Steam\nHumidifier\n(Condair/Hygromatik)"] G["Control\nPanel\n(KNX Gateway)"] H["Supply\nDuct\nManifold"]
|
||
end
|
||
|
||
style D fill:#1a5e1a,color:#fff
|
||
style E fill:#1a3d5e,color:#fff
|
||
style F fill:#1a5e5e,color:#fff
|
||
```
|
||
|
||
**All filter housings must be accessible from the front** with tool-free opening for filter changes. Minimum 800 mm clearance in front of each housing.
|
||
|
||
---
|
||
|
||
## 3. Duct Routing Requirements
|
||
|
||
### 3.1 Design Principles
|
||
|
||
| Requirement | Detail |
|
||
|------------|--------|
|
||
| Duct material | Rigid galvanized steel or aluminum — **no semi-rigid flex** |
|
||
| Exception | Final 0.5 m to each diffuser: flex for vibration isolation |
|
||
| Sealing | All joints mastic-sealed (not tape only) |
|
||
| Testing | Pressure-tested to Passivhaus duct leakage class after installation |
|
||
| Velocity: main trunk | ≤ 2.0 m/s |
|
||
| Velocity: branches | ≤ 1.5 m/s |
|
||
| Velocity: diffuser connection | ≤ 1.0 m/s |
|
||
| Main trunk diameter | 200–250 mm round (or equivalent rectangular) |
|
||
| Branch diameter | 125–160 mm round |
|
||
|
||
### 3.2 Routing Constraints
|
||
|
||
- **No ducts in exterior walls** — condensation risk and thermal bridging
|
||
- **Dedicated vertical risers** for multi-story distribution — coordinate with structural plan
|
||
- **Acoustic silencers** at MVHR outlets and before each room diffuser
|
||
- **Inspection/cleaning access points** at all bends > 45° and every 6 m of straight run
|
||
- **Fire dampers** at all floor/wall penetrations per DIN 4102
|
||
|
||
### 3.3 Duct Space Requirements
|
||
|
||
```mermaid
|
||
flowchart TD
|
||
subgraph Ground["Ground Floor Ceiling Void"]
|
||
GT["Main Supply Trunk\n200–250mm"]
|
||
GB1["Branch: Living Room\n160mm"]
|
||
GB2["Branch: Kitchen\n125mm (exhaust only)"]
|
||
GB3["Branch: Office\n125mm"]
|
||
end
|
||
|
||
subgraph Upper["Upper Floor Ceiling Void"]
|
||
UT["Main Supply Trunk\n200mm"]
|
||
UB1["Branch: Master Bedroom\n160mm"]
|
||
UB2["Branch: Leo's Room\n125mm"]
|
||
UB3["Branch: Bathroom(s)\n100mm"]
|
||
end
|
||
|
||
TR["Technical Room"] --> GT
|
||
TR --> UT
|
||
|
||
style TR fill:#1a3d5e,color:#fff
|
||
```
|
||
|
||
**Baufritz must allocate ceiling void depth of ≥ 300 mm** in areas where main ducts run, or provide dedicated duct boxing. This must be shown on construction drawings.
|
||
|
||
**Note**: The ceiling void is shared with the Lindner Plafotherm radiant ceiling system (see 04-flooring-ceiling-spec Section 4). On the ground floor, branch supply ducts may route through the raised floor cavity instead (see 04-flooring-ceiling-spec Section 6), potentially reducing ceiling void requirements. However, the main supply trunk and Plafotherm pipes still require adequate ceiling void depth. **Floor-to-floor structural height must be ≥ 3000 mm** to accommodate both the raised floor and ceiling system while maintaining ≥ 2500 mm usable room height (see 04-flooring-ceiling-spec Section 2).
|
||
|
||
---
|
||
|
||
## 4. Building Envelope Requirements
|
||
|
||
### 4.1 Airtightness
|
||
|
||
| Parameter | Requirement |
|
||
|-----------|-------------|
|
||
| Blower door test (n50) | ≤ 0.6 ACH (Passivhaus standard) |
|
||
| Target | 0.3 ACH if achievable |
|
||
| Testing | Blower door test during construction (before interior finishing) AND after completion |
|
||
|
||
Baufritz typically achieves excellent airtightness. This is critical — the air system only works if 100% of air passes through the filter stack. Every uncontrolled leak bypasses the entire system.
|
||
|
||
### 4.2 Radon Protection
|
||
|
||
| Item | Specification |
|
||
|------|--------------|
|
||
| Radon membrane | Continuous radon-proof membrane at foundation/ground slab |
|
||
| Membrane type | HDPE or bituminous, radon-tested per DIN/ISO |
|
||
| Sealing | All penetrations (pipes, cables) sealed with radon-rated sealant |
|
||
| Sub-slab ventilation | Provision for passive sub-slab depressurization (can be activated later if needed) |
|
||
| Monitoring | Radon sensor in lowest habitable room, connected to Home Assistant |
|
||
|
||
**Note**: The Bremen/Grasberg area is generally low radon risk per BfS (Federal Office for Radiation Protection) maps, but radon protection is inexpensive at construction stage and expensive to retrofit. Specify it regardless.
|
||
|
||
**Raised floor compatibility**: The Lindner NORTEC Doppelboden pedestal system must be anchored with adhesive bonding only — no mechanical fixings that penetrate the radon membrane. Verify adhesive compatibility with the membrane material (see 04-flooring-ceiling-spec Section 7.5).
|
||
|
||
### 4.3 Thermal Bridge Prevention
|
||
|
||
Baufritz excels at thermal-bridge-free construction. Verify:
|
||
- No thermal bridges at window reveals, sills, lintels
|
||
- No thermal bridges at floor/wall junctions
|
||
- No thermal bridges at balcony connections (if any)
|
||
- Surface temperatures never below dewpoint at any point (prevents condensation → mold)
|
||
|
||
---
|
||
|
||
## 5. MVHR Specification for Baufritz
|
||
|
||
### 5.1 Unit Selection
|
||
|
||
Specify to Baufritz that the MVHR unit must meet:
|
||
|
||
| Parameter | Minimum | Preferred |
|
||
|-----------|---------|-----------|
|
||
| Available static pressure | 450 Pa | ≥ 500 Pa |
|
||
| Airflow capacity | 400 m³/h | 450 m³/h |
|
||
| Heat recovery | 85% | ≥ 90% |
|
||
| Fan motor | EC variable speed | EC variable speed |
|
||
| Bypass | Summer bypass with motorized flap | Automatic |
|
||
| Controls interface | Modbus | KNX native |
|
||
| External filter box | Compatible | Designed for |
|
||
|
||
### 5.2 Baufritz-Typical vs. Our Requirements
|
||
|
||
Baufritz typically installs standard residential MVHR units (e.g., Zehnder ComfoAir Q350, Paul Novus 300). These are excellent units but designed for F7/F9 filtration with ~200–250 Pa system pressure.
|
||
|
||
**Our H13 whole-house requirement means upgrading to a higher-pressure unit.** This must be specified early because:
|
||
- The MVHR unit dimensions affect technical room layout
|
||
- Higher-pressure units may have different duct connection sizes
|
||
- Electrical requirements may differ (larger EC motors)
|
||
- Noise characteristics change — sound insulation may need upgrading
|
||
|
||
---
|
||
|
||
## 6. Garage Separation
|
||
|
||
If the house includes an attached garage:
|
||
|
||
| Requirement | Detail |
|
||
|------------|--------|
|
||
| Pressure separation | Garage at negative pressure relative to house |
|
||
| No shared air volume | No door directly from garage to conditioned space without airlock |
|
||
| Separate exhaust | Garage has its own exhaust fan with timer/CO sensor |
|
||
| Sealing | All wall/ceiling penetrations between garage and house fully sealed |
|
||
| CO sensor | In garage, interlocked with garage exhaust fan |
|
||
|
||
**Garage exhaust fumes (CO, NOx, PM, benzene) are extremely hazardous. Zero tolerance for garage air entering the conditioned space.**
|
||
|
||
---
|
||
|
||
## 7. Kitchen Exhaust Specification
|
||
|
||
| Requirement | Detail |
|
||
|------------|--------|
|
||
| Type | Ducted to outside — NOT recirculating |
|
||
| Backdraft damper | Motorized, closes when hood is off |
|
||
| Duct material | Stainless steel or galvanized (grease-rated) |
|
||
| Interlock | Activates MVHR boost mode for make-up air |
|
||
| Separation | Never connected to the MVHR system |
|
||
| Fire safety | Fire damper at wall penetration |
|
||
|
||
---
|
||
|
||
## 8. Electrical & Wiring Coordination
|
||
|
||
### 8.1 Technical Room Electrical
|
||
|
||
| Circuit | Rating | Purpose |
|
||
|---------|--------|---------|
|
||
| MVHR dedicated | 230V / 16A | MVHR unit power |
|
||
| Humidifier dedicated | 230V / 16A (or 400V / 3-phase) | Steam humidifier (high wattage) |
|
||
| Controls | 230V / 10A | KNX power supply, gateway, sensors |
|
||
| RO booster pump | 230V / 16A | Reverse osmosis feed pressure (see 05-water-system-spec) |
|
||
| Distribution pump | 230V / 10A | Water distribution pressure |
|
||
| UV sterilizer | 230V / 10A | Post-storage UV-C sterilization |
|
||
| Recirculation pump | 230V / 10A | Hot water recirculation loop |
|
||
| Backup/spare | 230V / 16A | Future expansion |
|
||
|
||
### 8.2 Main Electrical Distribution
|
||
|
||
The total house electrical demand including the cellar datacenter requires a properly sized main distribution:
|
||
|
||
| Parameter | Specification |
|
||
|-----------|--------------|
|
||
| Main fuse | **3×80A** (400V 3-phase) = ~55 kW capacity |
|
||
| Main distribution board | Located in cellar electrical room (see 06-datacenter-spec Section 4.2) |
|
||
| Sub-boards | Ground floor, upper floor, technical room (air/water), cellar/datacenter |
|
||
| Surge protection | Type 1+2 SPD at main board |
|
||
| Metering | Smart meter with Home Assistant integration |
|
||
|
||
### 8.3 Building-Wide Wiring
|
||
|
||
| Item | Specification |
|
||
|------|--------------|
|
||
| KNX bus cable | To every zone (MVHR dampers, sensors) |
|
||
| Cat6a shielded | 2× per room (dual-purpose: data network + sensor — see 06-datacenter-spec Section 6.2) |
|
||
| Fiber backbone | 12-core OS2 single-mode from cellar to each floor (10G+ backbone) |
|
||
| 230V at sensor points | USB power for sensor units |
|
||
| Outdoor sensor cable | Weatherproof, north wall |
|
||
| ΔP sensor cabling | 5× runs from filter housing to control panel |
|
||
|
||
**All wiring must be specified on Baufritz's electrical plan before wall construction begins.** Retrofit wiring in a sealed timber-frame house is extremely difficult and expensive. The fiber and Cat6a backbone risers from the cellar must be coordinated with the elevator shaft and/or dedicated cable riser.
|
||
|
||
---
|
||
|
||
## 9. Construction Phase Checkpoints
|
||
|
||
### 9.1 During Construction
|
||
|
||
| Phase | Checkpoint |
|
||
|-------|-----------|
|
||
| Cellar construction | Reinforced concrete cellar complete, waterproofed, radon membrane sealed |
|
||
| Cellar construction | Elevator shaft cast, anchor bolt locations verified |
|
||
| Cellar construction | Cellar slab level tolerance verified (+/- 5 mm) for Baufritz erection |
|
||
| Cellar construction | Electrical conduits cast into cellar slab for riser penetrations |
|
||
| Foundation | Radon membrane continuous between cellar and ground floor |
|
||
| Framing | Elevator shaft opening integrated into ground floor structure |
|
||
| Framing | Duct routing voids verified, vertical risers in place |
|
||
| Framing | Ceiling void dimensions verified for Plafotherm + MVHR trunk |
|
||
| Pre-close | First blower door test (target ≤ 0.6 n50) |
|
||
| Pre-close | All duct runs installed, mastic-sealed, pressure-tested |
|
||
| Pre-close | All KNX/Cat6 wiring installed and tested |
|
||
| Interior finishing | Plafotherm ceiling suspension and panels installed |
|
||
| Interior finishing | Ceiling heating circuit pressure-tested |
|
||
| Interior finishing | Raised floor pedestals installed, subfloor leveling verified |
|
||
| Interior finishing | Under-floor services (ducts, wiring) installed and pressure-tested |
|
||
| Interior finishing | Floor panels and WOODline parquet tiles installed |
|
||
| Interior finishing | 316L stainless steel water supply runs installed in ceiling void |
|
||
| Interior finishing | Water supply pressure-tested at 16 bar for 2 hours |
|
||
| Interior finishing | All press-fit joints verified accessible via ceiling panel removal |
|
||
| Interior finishing | Drain/waste pipes installed in floor cavity |
|
||
| Interior finishing | Verify no ducts compressed or kinked by finishing work |
|
||
| Completion | Final blower door test |
|
||
| Completion | Commission MVHR, set airflows, balance dampers / AirHybrid panels |
|
||
| Completion | Commission ceiling heating/cooling, verify surface temperatures |
|
||
| Completion | Commission RO system, verify TDS/pH at every outlet |
|
||
| Completion | Commission leak detection, test auto shut-off valve |
|
||
| Completion | Elevator installed and tested |
|
||
| Completion | Datacenter racks, cooling, UPS commissioned (see 06-datacenter-spec Section 12) |
|
||
| Completion | Structured cabling (fiber + Cat6a) tested and certified |
|
||
| Completion | Commission sensors, verify readings, connect to Home Assistant |
|
||
|
||
### 9.2 Commissioning Verification
|
||
|
||
| Test | Acceptance Criteria |
|
||
|------|-------------------|
|
||
| Blower door (n50) | ≤ 0.6 ACH |
|
||
| Duct leakage | Passivhaus class |
|
||
| Room-by-room airflow | Within ±10% of design spec |
|
||
| House positive pressure | +3 to +5 Pa vs. outside |
|
||
| CO₂ decay test | < 800 ppm within 30 min of occupancy end |
|
||
| PM2.5 indoor vs. outdoor | Indoor < 10% of outdoor |
|
||
| Noise at diffusers | < 25 dB(A) per diffuser |
|
||
|
||
---
|
||
|
||
## 10. Timeline Integration
|
||
|
||
| Baufritz Phase | Air System Action | Lindner Floor/Ceiling Action | Water System Action | Cellar/Datacenter Action |
|
||
|----------------|-------------------|------------------------------|---------------------|--------------------------|
|
||
| Initial design | Specify MVHR unit, technical room size (8-10 m2), duct routing | Confirm raised floor + Plafotherm, specify cavity heights and floor-to-floor height (≥ 3000 mm) | Confirm POE RO location, municipal water entry, reject water drain | Cellar dimensions, elevator shaft location, main electrical sizing (3x80A) |
|
||
| Detailed planning | Approve duct routing on drawings, specify all penetrations | Lindner layout drawings for floor and ceiling, coordinate with MVHR plan | 316L pipe routing in ceiling void, riser locations, fixture drop-down points | Cellar structural drawings, elevator spec, cooling condenser location |
|
||
| Pre-fabrication | Confirm radon membrane spec, duct void dimensions | Verify subfloor level tolerance and ceiling anchor points in prefab panels | Confirm ceiling void can accommodate water pipes alongside MVHR and Plafotherm | **Cellar construction begins** (concrete, waterproofing, elevator shaft) |
|
||
| Factory build | Verify duct voids in prefab wall/floor panels | No impact (Lindner systems installed on-site) | No impact (water system installed on-site) | Cellar complete, slab cured, ready for Baufritz erection |
|
||
| On-site assembly | Supervise duct installation, first blower door test | Install ceiling suspension, route Plafotherm pipes | Install 316L supply mains in ceiling void (same phase as Plafotherm) | Elevator installed, main distribution board installed |
|
||
| Finishing | Sensor wiring, diffuser installation | Plafotherm panels, floor pedestals, parquet tiles | Pressure-test pipes, install drain/waste in floor cavity, connect fixtures | Datacenter fit-out: racks, cooling, cabling, UPS |
|
||
| Handover | Full commissioning, sensor calibration, HA setup | Heating/cooling commissioning, AirHybrid airflow verification | RO commissioning, TDS/pH verification, leak detection test | Cooling commissioning, fire detection test, HA integration |
|